Mars Global Surveyor Status


All activities of the Mars Global Surveyor (MGS) project are moving along well toward launch in early November.

The spacecraft assembly is nearly complete at the Lockheed Martin facility in Denver, Colorado, and has the spacecraft has begun its first fully integrated system electrical testing. All but two of the science instruments have been installed, and the remaining ones are due in May.

hga_instl8_final.jpg
Mars Global Surveyor High Gain Antenna being assembled at Lockheed Martin in Denver, CO

As is the case with many spacecraft, the mass of the assembled hardware always seems to be a little more than is predicted by the design documents. Such is the case with the MGS spacecraft. A considerable effort has been applied by the project team over the last few months to reduce the spacecraft mass and to find ways to change to mission plan to be able to accept a little heavier spacecraft and still be able to meet mission objectives. After all the studies were complete, and the mass of the all the spacecraft assemblies had been reassessed, we agreed on a 1060-kg upper limit total launch mass and slipped the opening of the launch period on day to open on November 6th. Some of the spacecraft's thermal blankets are the only remaining items yet to be weighed, but all indications are good that the mass limit will be met.

The end-to-end tests that assure compatibility between the flight operations system (which will be responsible for "flying" or controlling the spacecraft after launch) and the spacecraft itself are now underway, and the results are looking good.

The two remaining science instruments, the Thermal Emission Spectrometer and the Mars Orbiter Laser Altimeter, suffered minor setbacks during their final acceptance testing, and both required some reworking before final testing and delivery. The required rework is underway and is progressing well.

--Glenn E. Cunningham