5 p.m. Pacific Daylight Time
Mars Pathfinder lander and rover operations were curtailed
today when the lander downlink session, scheduled to begin at
1:20 p.m. PDT, was not initiated. The cause of the problem is
currently unknown, said Mars Pathfinder Mission Manager Richard
Cook.
The flight team, led by Flight Director Carl Steiner,
subsequently reestablished communications with the lander and
received a brief carrier blip at 3:30 p.m. PDT. Additional
downlink sessions were not attempted, however, because of the
lack of time before the Earth set over the landing site at 5:42
p.m. PDT.
Data on the health of the lander and rover, in addition to
other engineering telemetry, will be acquired tomorrow. The
flight team expects Sol 30 operations to proceed normally.
Additional information will be posted on the JPL home page
at http://www.jpl.nasa.gov as it becomes available. An audio
update is also available by calling 1-800-391-6654.
On this Martian day, Sol 29, Earthrise occurred at 4:09 a.m.
PDT and sunrise followed at 7:11 a.m. PDT. The sun set over the